  • BJ完成尼日利亞海底管線預鋪設(英)

    [加入收藏][字號: ] [時間:2009-11-13  來源:全球石油網  關注度:0]
    摘要:簡介:BJ公司最近在尼日利亞完成一項重要海底管線工程的部署工作,該項目是Saipem 在尼日利亞的一個超深水Akpo項目。 BJ Services Company recently completed a major subsea p...
    簡介:BJ公司最近在尼日利亞完成一項重要海底管線工程的部署工作,該項目是Saipem 在尼日利亞的一個超深水Akpo項目。

    BJ Services Company recently completed a major subsea pipeline precommissioning operation for Saipem offshore Nigeria on the Akpo development, one of the largest deepwater developments ever undertaken.

    Akpo is a gas and condensate field in the Oil Mining Lease 130 Block, approximately 124 miles (200 km) south of Port Harcourt, Nigeria, and operated by Total Upstream Nigeria, a Total subsidiary, on behalf of license partners CNOOC, Petrobras, and Sapetro. Akpo has proved and probable reserves estimated at 620 million bbl of condensate and greater than 1 Tcf of gas, and is being developed through 44 subsea wells tied back to the Akpo Floating Production Storage and Offloading (FPSO) vessel, which accepts the condensate. The gas is piped 150 km to the Amenam/Kpono platforms, from where it will be sent to the Bonny liquefaction plant.


                                     The Akpo FPSO. 

    The wells are placed at water depths between 3,936 ft and 4,593 ft (1200 m to 1400 m). At these depths, flooding and testing a pipeline with a conventional vessel-based pumping spread becomes quite challenging and costly, as the large pressure drop down the long pipeline necessitates an increase in diameter.

    To circumvent these challenges, Saipem awarded BJ Services a contract in March 2008 to supply a complex series of precommissioning services on the Akpo flowlines and umbilicals in three main phases:

    Phase 1 involved precommissioning the gas export line, which is a 16-in. pipeline that stretches 91 miles (147 km)
    In Phase 2 the production, water-injection, gas-injection, and oil-offloading lines were precommissioned. The overall flowline precommissioning workscope included post-lay flooding, cleaning, and gauging pigging; post-tie-in hydrotesting; dewatering; drying; and nitrogen-packing services
    Phase 3 involved precommissioning of the infield static and dynamic umbilicals, which range in length from 3 to 6 miles (5 to 10 km). This included a full range of hydraulic and electrical testing

    BJ Services' RFM, ready for deployment.
    For this scope of work, BJ Services employed its Remote Flooding Module (RFM), which allows lines to be flooded with treated, filtered seawater without connection to a vessel. The unit, which includes the required filtration and chemical-injection systems, uses the hydrostatic head available outside the empty pipeline to flood the line with seawater. Once the hydrostatic head is equalized, a boost pump powered by a remotely operated vehicle (ROV) is used to propel a pig through the line to a receiver. If required, an ROV-powered subsea hydrotest pump can be used to hydrotest the pipeline subsea.

    All of these benefits serve to reduce vessel time and related costs. In addition, safety is enhanced because the process is carried out without a downline and diesel-pumping spread, and impact on the environment is reduced because no byproduct from the diesel engines is released into the atmosphere.

    Work was carried out from the deepwater support vessel Bourboun Trieste and the Akpo FPSO by BJ Services personnel with equipment from the company’s base in Port Harcourt.

    This project is the latest in a long series of pipeline precommissioning operations that BJ Services has performed for Saipem throughout the world, the first of which was carried out in another Nigeria project in 1997.

    “We have forged an enduring and mutually beneficial working relationship with Saipem in Nigeria, and are extremely fortunate to have been given the opportunity to work on the Akpo Development,” said Lindsay Link, general manager, BJ Services, Process and Pipeline Services. “The operation was especially challenging, given the complexity of the subsea pipeline network and the deepwater environment. As the direct result of the Akpo team’s commitment and experience, and the specialist technologies used, I am pleased to report that it was carried out safely and efficiently,” he added.

    For more information visit the company’s web site at www.bjservices.com .

              您的分享是我們前進最大的動力,謝謝!
    關鍵字: BJ 海底管線 
    關于我們 | 會員服務 | 電子樣本 | 郵件營銷 | 網站地圖 | 誠聘英才 | 意見反饋
    Copyright @ 2012 CIPPE.NET Inc All Rights Reserved 全球石油化工網 版權所有
    京ICP證120803號 京ICP備05086866號-8 京公網安備110105018350
    国产精品国产三级国产AⅤ| 成人国产精品2021| 久久精品青青大伊人av| 国产精品亚洲美女久久久| 亚洲欧洲日韩在线电影| 午夜精品福利影院| 99久久99这里只有免费费精品| 久久香蕉超碰97国产精品| 国产午夜福利精品一区二区三区| 国产精品黄页免费高清在线观看| 日韩精品午夜视频一区二区三区| 国产精品videossex另类| 性感美女视频在线观看免费精品| 国产精品一久久香蕉国产线看 | 亚洲国产精品无码av| 999成人精品视频在线| 精品久久久久久无码人妻蜜桃| 精品一区精品二区| 亚洲日韩精品无码专区加勒比| AV在线播放日韩亚洲欧| 国产成人一区二区精品非洲| 国产精品美女网站在线看| 精品久久中文字幕有码| 九九热线精品视频16| 中文字幕久久久久久精品| 亚洲精品无播放器在线播放| 国产精品亚洲综合久久| 无码成人精品区在线观看| 国产精品久久一区二区三区| 亚洲精品偷拍无码不卡av| 精品亚洲国产成AV人片传媒| 亚洲精品高清国产一久久| 99ri在线精品视频| 精品无码国产污污污免费网站国产| 国产精品原创巨作?v网站| 久久精品无码av| 思99热精品久久只有精品| 国产精品丝袜一区二区三区| 亚洲av无码国产精品夜色午夜| 少妇伦子伦精品无码STYLES| 99久久人妻精品免费二区|